GENERAL ELECTRIC signed a contract for a brand new
gas-fired thermal power plant within Kiel, Germany, delivering twenty Jenbacher
J920 Flextra fuel engines with a power outcome of 190 MW, that represents the
largest sale within the history of the Jenbacher organization, GE said.
General service provider Kraftanlagen München (KAM)
will certainly build the plant on behalf of city and county utility Stadtwerke
Kiel. The brand new power plant will replace the current coal-fired community
power plant and can supply the region with region heating.
Twenty Jenbacher J920 FleXtra gas engines will give a
total output of one hundred ninety MW electrical and hundranittiotv? MW thermal
power, which is fed into the electrical as well as district heating network. The
entire efficiency of the equipment through GE is greater than 九成, while electrical efficiency is actually
45%, GE said. The organization added that the marketing associated with
balancing energy and the incorporation of an electrode boiler (power-to-heat)
during periods of lower electricity prices provide a versatile and economical
solution. This particular ensures not only the local supply, but also guarantees
functional cost-effectiveness. Compared with the previous coal-fired power
plant, CO2 emissions tend to be reduced from 1 . eight million tonnes to around
540 000 tonnes.
“The new gas-fired
thermal engine power in Kiel is a innovative example for the successful
recognition of the energy transition strategy by employing highly efficient
mixed heat and power era, ” said Gerrit Koll, business unit leader, power and
power plant technology in KAM.
The greatest possible versatility was a primary
requirement of the brand new Stadtwerke Kiel plant, stated GE. Due to the high
percentage of wind-generated electricity inside the regional grid, the power
flower has to be able to feed complete power into the local electric grid within
a short period to be able to offset the volatility from the wind level, thus
making sure stability of the grid. The actual Jenbacher J920 FleXtra gasoline
engines can be called up to their own full capacity in just a couple of
minutes.
The order from Stadtwerke Kiel is divided into 2
phases. The initial project requires the planning and construction in the pump
house to connect towards the district heating system, the electrode boiler and
heat storage space as well as scheduling and acquiring operating approval for
the entire program, including gas engines. The 2nd phase of the project, such as
construction of the gas motor power plant, is scheduled to become underway
starting in Might 2016.